Aultmore Wind Farm

In February 2014 Moray Council granted planning permission for Aultmore Wind Farm.   The application received widespread support.  We would like to thank the local community and businesses for their continued support.

Wind-turbine

The project is situated in Aultmore Forest, Banffshire approximately five miles north of Keith and four miles south of Buckie in Moray, Scotland.  When constructed, the wind farm, which is in a forested site managed by Forestry Commission Scotland will comprise of 13 turbines, with an expected installed capacity of 29MW.

Keeping you informed

Our project team will continue to work closely with the local community.  We are currently putting together a timetable for planning condition discharge and a forward construction programme.

We are committed to providing a community benefit package for the 25 year life of the project, which will be developed in dialogue with the local community.  We will look to continue dialogue on the principles and practicalities of establishing the community benefit fund so that the best and most appropriate fund is developed to meet the needs of the local community.

Local supply chain opportunities in Aultmore

Vattenfall is committed to engaging with local companies to ensure that our approach to project procurement and investments supports local businesses to enter and prosper in the renewable energy and green jobs sector. We plan to hold supply chain events early next year. Please register your interest here.

Expected Timeline:

  • February 2014 Positive Planning Decision
  • Q2 2014 Begin work to discharge planning conditions
  • Q1 2015  Supply chain event
  • Q2 2015  Tender major contracts
  • Q1 2016  Award contracts
  • Q1 2016  Start construction
  • Q2 2017  Operational Site
  • Q2 2017  Launch community benefit fund